Timeline for Requesting a New Multimedia
Installation
Funded by Departments
June 1 – August 31
Multimedia installation requests are sent by department head(s) to Multimedia
Services.
September 1 – October 31
Multimedia Services:
- walks through rooms with Physical Plant and Network Services
- researches equipment, and creates room estimates
- sends estimates back to department head(s)
November 1 – January 31
Department head(s) decides on which projects will proceed.
February 1 – March 31
Multimedia Services:
- orders equipment
- schedules work for Physical Plant
- schedules work for Network Services
April 1 – May 31
Multimedia Services:
- receives equipment
- labels equipment
- completes necessary paperwork
- prepares equipment for installation
June 1 – August 31
Multimedia Services:
- installs equipment
- tests equipment
- provides room briefings to department
|